Why Public Projects Need Design Criteria Documents

If you’ve been in public construction long enough, you’ve heard the term or some version of it: design criteria package, bridging documents, performance criteria, basis of design, owner’s project requirements, project definition documents, design intent documents, or sometimes just “the criteria.” The names change depending on the delivery method, the state statute, the project type, or simply who’s leading the conversation, but the confusion goes beyond terminology. Ask five people what a criteria document actually is and you’ll get five different answers, with some describing it as early design, others calling it a programming document, and others defining it strictly as a procurement tool. The reality is that it’s all of these things and none of them individually, and that lack of a shared definition is part of why so many projects get it wrong.

Whatever name it goes by, the document exists to solve the same problem. Every project starts with a gap between what the owner needs and what the design team knows, and that gap gets filled one way or another. It either gets filled deliberately, through a structured process, such as a visioning session, that captures requirements, reconciles competing priorities, and documents decisions with contractual weight, or it gets filled by assumption, by whoever happens to be making choices at the time. A criteria document is the deliberate version, and it is used across healthcare, higher education, transportation, and federal government construction because the alternative (letting requirements live in emails, meeting notes, and verbal agreements that no one has formally approved) consistently produces scope disputes, cost overruns, and buildings that don’t work the way they were supposed to. That risk exists in any delivery method, but it compounds more heavily when the owner is handing design authority to someone else.

Why Courthouses, Jails, and Detention Facilities Raise the Stakes

Justice facility projects raise the stakes even further. Courthouses, detention facilities, and public safety buildings carry a level of operational complexity, security integration, and multi-agency coordination that goes far beyond what a standard program or set of specifications can capture, and unlike federal courthouse projects that can reference the U.S. Courts Design Guide, most state and local justice projects have no statewide or agency-wide design standards to fall back on. Every jurisdiction operates differently, with its own caseload mix, staffing model, security philosophy, and statutory requirements. No two courthouses operate the same way, and neither do any two jails.

A criteria document is what fills that gap, translating the specific operational realities and agency needs for a particular facility into requirements that a design team can actually work from.

How Design-Build Growth and State Law Are Raising the Bar

The need for criteria documents has only grown as the industry has evolved. Three shifts are driving that growth: design-build’s rising share of construction spending, delivery methods that move design control away from the owner, and a growing number of states codifying criteria document requirements in statute. How these documents are defined, who prepares them, and what they must contain varies widely from state to state, and understanding that landscape is essential to getting them right. A criteria document that is too vague leaves the design-builder to fill in the gaps on their own, while one that is too prescriptive limits competition, discourages innovation, and transfers design liability back to the owner.

The discipline of preparing these documents is often called criteria architecture. What follows is a primer on what these documents include, who should prepare them, how they work in practice, and what defines an effective approach to criteria architecture.

 

What Are Design Criteria Documents, and What Do They Include?

A design criteria document is a coordinated package of narratives, performance specifications, and indicative drawings that defines what a building must do before anyone decides what it will look like.

That is the intent. In practice, many fall short.

If you’ve ever opened a criteria document and found hundreds of pages of requirements with no clear hierarchy, no way to tell what’s mandatory versus preferred, and no organizational logic beyond the order in which stakeholders submitted their wish lists, you already know the problem. The information is there, but the structure isn’t.

Nobody filtered competing requirements against a shared set of priorities, nobody resolved the contradictions between what the tenants need and what the owner can afford, and nobody made clear which requirements carry contractual weight and which are preferences that disappear when the budget gets tight. What you’re left with is a document that either gives the design-builder enough ambiguity to interpret it however they want or buries them in so much prescriptive detail that there’s no room left for competition or innovation.

Three Tests for Every Requirement: Mission, Function, and Execution

The criteria documents that work best avoid both of those traps by organizing every requirement around three questions:

    1. Does it support the mission, meaning the core operational purpose of the facility?
    2. Does it support function, meaning the efficient movement of people, delivery of services, and daily operation of the building?
    3. Is the execution realistic, meaning it can be built within the constraints of budget, schedule, and long-term maintainability?

These three filters give both the owner and the design team a shared language for evaluating what belongs in the document, what doesn’t, and how to resolve the inevitable conflicts between competing stakeholder priorities. These tests only work when the document rests on a clear foundation.

The Foundation of Criteria Architecture: Regulatory Requirements and Owner’s Intent

Before any of that filtering can happen, the document needs a foundation, and that foundation has two layers. The first is the regulatory context: the building codes, accreditation requirements, and state or local compliance mandates that apply to the facility type and jurisdiction. The second is the owner’s intent: what the facility is trying to accomplish operationally, what populations it will serve, what staffing model it will support, what security philosophy will guide the design, and what level of quality, durability, and sustainability the owner expects over the building’s lifecycle. Everything in the criteria document should be traceable back to one of these two layers, and if a requirement can’t be tied to either regulatory compliance or the owner’s stated goals, it probably doesn’t belong in the document.

What a Design Criteria Package Includes

With that foundation in place, the criteria take shape as a coordinated package of four components:

  • Narrative descriptions that explain operational requirements, adjacency relationships, security protocols, and interior requirements.
  • Master planning and site utilization documents that address building placement, infrastructure, parking, and expansion capacity.
  • Performance specifications that establish measurable baseline standards for significant elements of building systems, materials, and equipment, leaving room for creativity without specifically ordering how the element is executed.
  • Indicative drawings, ranging from schematic diagrams to conceptual layouts, that convey spatial relationships, functional configurations, and adjacencies without prescribing specific design solutions. 

For justice facilities in particular, how a building operates determines how it needs to be designed, not the other way around. Sometimes the criteria document’s greatest value is in memorializing the operations and procedures that have been in place for decades and will continue into the future, but, just as often, these projects are once-in-a-lifetime opportunities to rethink how a facility functions. The way a courthouse or jail operates today may not reflect where the jurisdiction is headed, and caseload growth, policy shifts, changes in supervision philosophy, new technology, and evolving standards of care all reshape how these buildings need to perform over time. A criteria document must capture both, what works now and what will need to work in the future, and getting that right depends entirely on who is preparing it.

 

Who Prepares Criteria Documents? The Criteria Architect’s Role by Delivery Method

It comes as a surprise to many, but the criteria architect and the design architect are two different roles. The criteria architect’s job is to define what the building must do, while the design architect’s job is to figure out how the building does it. When those roles get blurred (or when the criteria document is treated as the first phase of design rather than the last phase of planning) the document tends to drift toward design solutions instead of holding the line on requirements, and the owner loses the objectivity that makes the document valuable in the first place.How the criteria architect fits into the project depends on the delivery method.

Design Criteria Documents in Design-Bid-Build Projects

In a traditional design-bid-build project, the criteria document functions primarily as an internal governance tool, with the owner retaining the architect, controlling the design, and using the criteria as a reference to make sure the design stays aligned with the facility’s operational needs. The design architect may even be the one who prepares it, because the owner maintains oversight throughout the process, the feedback loop is continuous, and course corrections can happen in real time.

Design Criteria Documents in Design-Build Projects

The situation changes significantly in design-build, where the design-builder controls both design and construction under a single contract and the criteria document becomes the owner’s primary mechanism for defining what the project must deliver. It is no longer internal guidance, it is the contractual standard against which proposals are evaluated, scope is measured, and the finished building is judged.

State Design-Build Laws That Govern Criteria Documents

Several states have written criteria requirements into statute, each with a different emphasis:

  • Florida §287.055 requires the criteria document to be prepared and sealed by a licensed design criteria professional who is barred from bidding on the design-build contract.
  • Texas Gov Code §2269.306 mandates a criteria package prepared by licensed professionals that includes detailed information for a design-build firm to prepare a response to a request for qualifications (RFQ). In this package, criteria necessary to describe the project may include requirements for quality assurance and quality control in addition to space requirements, cost or budget estimates, site development, and provisions for utilities, amongst other requirements.
  • Ohio §153.65 goes further by codifying the role of a “criteria architect or engineer” in statute. It’s one of the few states to put that title in law and defines their responsibility from establishing criteria through verifying design intent during construction.
  • North Carolina §143-128.1B sets a specific design completion threshold, requiring the criteria package to reach thirty-five percent before procurement can move forward.
  • California Gov Code §13332.19 requires “performance criteria” prepared by a licensed professional and adds a layer of state-level oversight, with the Department of Finance and State Public Works Board approving the criteria before the project goes to solicitation.

Design Criteria in CMAR and Public-Private Partnerships (P3)

Other delivery methods carry their own nuances:

    • In CM-at-Risk (CMAR), the criteria document plays a less prominent but still important role, informing the architect during design and establishing the scope baseline from which the guaranteed maximum price is eventually negotiated, typically after the design reaches a defined percentage of completion.
    • In Public-Private Partnerships (P3), the criteria document has to go further, because P3 structures, like design-build-finance-operate-maintain, make the private partner responsible for the facility not just through construction but for decades of operations afterward. That means the criteria must define performance and maintenance standards tied to availability payments over the life of the concession, not just what gets built but how it performs over time and the consequences when it doesn’t. P3 remains relatively rare in justice facility delivery, but as enabling legislation expands and public budgets tighten, the criteria document becomes the owner’s primary safeguard against a building that works on day one and deteriorates steadily under a contract that makes it difficult to intervene.

 

How to Choose a Criteria Architect for a Justice Facility Project

Even with the best structure and framework in place, the wrong team invalidates the best process. The right criteria architect is someone who has been in the design architect’s shoes and understands the competitive bidding environment from the inside, who knows what proposers need to see in a criteria document to price it accurately, but who also brings deep insight into how the owner operates, how the facility is staffed, how decisions get made on the ground, and what the building actually needs to do 20 to 50 years after the ribbon cutting. That combination is rare, because it requires someone who can think like a designer, communicate like a procurement professional, and plan like an operator.

Finding the right criteria architect is also harder by the nature of the role itself: in many states, the firm that prepares the criteria document is prohibited from competing for the design-build contract, which means highly qualified teams often have a financial incentive to skip the criteria work and position themselves for the larger project instead. The owner is left choosing between a team that knows the building type but wants the bigger fee, and a team that’s available but may not have the depth of experience to get the criteria right.

Striking that balance – finding the team that has the expertise, the independence, and the willingness to do the work without angling for what comes after it – is one of the most consequential decisions an owner will make on a justice facility project. But even then, getting the right team to write the document is the first battle. The second is making sure it doesn’t sit on a shelf once the contract is signed.

How Are Design Criteria Documents Used After They Are Written?

A criteria document that lives in a binder after contract award is just an expensive planning exercise. Its value shows up in two critical phases: procurement and selection, and design and construction, and in each phase, it serves a different function.

During Procurement: Comparing Design-Build Proposals on Equal Terms

During procurement and selection, the criteria document levels the playing field. Every technical requirement in the RFP should trace back to a specific provision in the criteria, which means every proposer is bidding against the same set of assumptions, the same performance standards, and the same scope definition. Without that consistency, firms fill in the blanks differently, price different versions of the project, and produce proposals that are nearly impossible to compare on equal terms. The criteria document also creates a transparent and defensible basis for scoring: when the evaluation committee can point to specific criteria that one proposal met and another didn’t, the selection holds up under scrutiny and protest. It establishes how deviations are handled, whether alternatives are permitted, how they will be evaluated, and whether they affect scoring, so that proposers know the rules before they invest in a response and the owner isn’t making those decisions under pressure after proposals are in.

During Design and Construction: Resolving Scope Questions Before They Become Disputes

During design, and especially in early schematic phases, is where the criteria document pays for itself. Without one, the design team spends weeks or months pulling requirements out of individual stakeholders one meeting at a time, revisiting decisions that were supposedly settled, and mediating conflicts between agencies that should have been resolved before design ever started. A well-prepared criteria document compresses that process dramatically, because the requirements have already been documented, vetted, and approved. The design team can move straight into solving problems rather than defining them, and the owner’s team isn’t pulled into every design meeting to re-explain how the building needs to operate.

When design starts testing the boundaries of the criteria (and it always does), the document provides the basis for resolving those conflicts on the merits of the requirements rather than the preferences of whoever is in the room. During construction, the criteria document continues to serve as the neutral reference point for scope disputes and change orders, but the real savings happen earlier, in the design phases that don’t get derailed by decisions that should have been made before the first line was ever drawn.

 

Best Practices for Design Criteria Documents: From Early Design to Decision Architecture

Most architectural and engineering firms treat the criteria document as early design, a preliminary version of the drawings and specifications that will eventually become the construction documents. We treat it as something fundamentally different: decision architecture. The distinction matters because it changes what the document prioritizes, how it’s organized, and what it’s designed to protect.

Where a traditional criteria author focuses on form and systems, we have recognized that operations, risk, and lifecycle are equally important. Where a traditional approach is driven by schematic design and treats cost as an estimate, more effective approaches build performance-driven requirements evaluated through a total cost of ownership lens. And where most criteria documents stop at design intent, they should address design, activation sequencing, staffing, and long-term maintenance intent, because a building that works on paper but fails operationally is a building that failed its criteria.

This belief is deeply rooted in what we do beyond criteria work. Our in-house maintenance technicians work in more than 19 million square feet of public and justice facilities, which means the people informing our criteria have direct, daily knowledge of how these buildings actually perform after the construction team leaves. That feedback loop, from operations and maintenance back into criteria development, is what allows us to embed classification logic, staffing models, and security philosophies directly into the document rather than leaving them for the design-builder to interpret. It’s also how we anticipate activation sequencing and transition risk, two areas that most criteria documents ignore entirely but that consistently drive cost overruns and operational disruptions on justice facility projects.

Based on our experience working with justice facility owners, we’ve compiled the following list of best practices that should be adopted when preparing criteria documents:

  • Begin with a review of the existing planning study and program to develop a complete understanding of the owner’s goals and objectives. When this foundational work has been considered but not completed (a common situation in justice facility development) it’s important to supplement with a qualified research, analysis, and forecasting team, who will work with the owner to examine historical patterns, define the desired future state, and determine what a new facility may require. This knowledge and scientifically backed baseline then move into program development (or validation, if a program exists), site assessment and master planning, operational analysis, and alternatives development before the criteria package is assembled.
  • At every stage, filter the work through the same mission, function, and execution framework described earlier in this guide – don’t treat it as an abstract organizing principle.
  • Staff criteria teams with people who have operated these buildings, maintained these systems, and managed these populations, so the filters are grounded in firsthand experience rather than theoretical best practice. That framework carries forward into design oversight. Specialized review tools have been developed that allow owners to accept or reject design submittals at each milestone by measuring every submission against the documented criteria rather than reacting to drawings in real time. It gives both the owner and the designer a structured process for tracking progress and resolving disagreements before they become disputes.
  • Approach criteria through a Total Cost of Ownership (TCO) model. Over the life of a justice facility, capital construction represents a fraction of the building’s total expense, with staffing, maintenance, and utilities making up the majority. Effective criteria documents account for that reality, because a requirement that saves money during construction but adds cost every day the building operates isn’t a savings at all.
  • Don’t approach criteria as a one-time engagement. The owners working on criteria architecture today will feel the impacts of their decisions for years to come – whether that’s on the next project, through facility management, or navigating a course of action when the building needs to adapt to something nobody anticipated. That long view shapes how criteria should be written, because it shouldn’t be optimized for a deliverable, it should set the foundation for outcomes that will last throughout the life of the facility and serve the community well.

That is the difference between criteria as early design and criteria as decision architecture. One is a document. The other is a commitment.

 

Getting Design Criteria Right Starts with the Right Team

A criteria document is only as strong as the people who shape it. The owners who get the most from the process pair their internal team with a partner whose experience spans planning, design, procurement, operations, and long-term maintenance, so every requirement is tested from each of those angles before it carries contractual weight. If your jurisdiction is weighing a new courthouse, jail, or detention facility, bringing in that breadth of experience early puts the project on its strongest path forward.

Meet the Authors

9148Design Criteria Documents for Justice Facilities: What They Include, Who Prepares Them, and How to Use Them

Eftalia Proios Torras

Associate VP, Design Services

Eftalia brings nearly a decade of experience designing large-scale civic and justice facilities across the U.S. and internationally. She focuses on creating environments that support equity, sustainability, and community well-being through trauma-informed and restorative design principles. Eftalia collaborates closely with clients and project teams to ensure each design reflects program goals and operational needs. With expertise in BIM integration, sustainable strategies, and inclusive design, she has contributed to millions of square feet of public-sector space. Her multidisciplinary background and global...

5579Design Criteria Documents for Justice Facilities: What They Include, Who Prepares Them, and How to Use Them

Tamara Clarke

Director of Design Services

Tamara has over 35 years of experience, including over two decades dedicated to justice and civic architecture. She has led the design and delivery of complex facilities across the country, including detention centers, courthouses, forensic labs, and behavioral health spaces. Tamara is known for her thoughtful, human-centered approach that balances innovation with functionality to support diverse user needs. A recognized leader in the justice design community, she actively contributes to national conversations on design and sustainability and has held leadership...